LTSD Building Project

LTHS/LTMS Renovation Information

Please use this page for information on the building project at LTHS/LTMS

 

Progress as if 1/9/2024
    Progress as of 8/8/2023

Progress as of 6/9/2023

Progress as of 5/24/23
Progress as of 4/19/23
New Gymnasium New Gymnasium New Gymnasium
Gymnasium Entrance Health Classroom #1 Health Classroom #2
Concession Stand Men’s Restroom Women’s Restroom
Hallway to Existing School Hallway to outside entrance from Gymnasium Music Classroom
Music Classroom

Progress as of 10/24/2022

West Gym Wall North Gym Wall Northwest Gym Wall
New Gym Vestibule/Entrance New Gym Interior New Health Education Classrooms
New Gym Interior Looking West New Addition Facing Existing School
New Concession Stand Workers Side New Concession Stand Customer Side New Multi-Purpose Room
New Multi-Purpose Room New Multi-Purpose Room New Training Room

Site Visit Report – Sep 25, 2023

Site Visit Report – Aug 28, 2023

Site Visit Report – May 5, 2023

Site Visit Report – April 24, 2023

Site Visit Report – April 14, 2023

Timeline Report – April 12, 2023

Site Visit Report – March 13, 2023

Site Visit Report – January 4, 2023

Site Visit Report – December 19, 2022

Site Visit Report – November 21, 2022

Site Visit Report – November 7, 2022

Site Visit Report –  October 24, 2022

Timeline Report – Revised October 10, 2022

Site Visit Report – October 2022

Student Driver Instructions for Parking 2022-23 

LTHS/MS Baseline Schedule

LTHS/LTMS Building Plan Blueprint

LTHS/LTMS Building Project FAQs

LTHS/LTMS New Traffic Pattern during Construction – Updated 9/28/2022

 Multipurpose Room Walkthrough Video
Gym Addition Walkthrough Video
East Wing Cafe and Classroom Additions

 